RAJOURI, AUGUST 16:– District Development Commissioner Rajouri, Vikas Kundal today took a comprehensive review of the RDD sector here in a meeting of the concerned officers.
During the meeting, threadbare discussion on various points including District Capex budget, Amrit Sarovar, PMAY, Awas plus, 14th FC, soak pits, secure status of estimation, timely payments, progress under PDs generation etc was held.
Discussing the progress made under the District Capex budget, the meeting was informed that out of 3786 approved works, as many as 3405 works have been put to tenders while 170 works have been allotted for execution. DDC asked the concerned officers to ensure that all the works are alloted and completed in time.
Seeking the progress under person days generation, it was apprised that 343618 PDs have been generated as on date. DDC asked to take effective measures to meet the yearly target well before the completion of this financial year.
Taking stock of the status of secure estimation, it was given out that 28827 works are on the shelf for FY 2022-23 and 11052 MGNREGA works have been sent to secure.
While reviewing the progress under soak pits construction, the meeting was informed that against the target of 130000 units, the work on 23221 units in progress. Regarding Amrit Sarovars, it was apprised that out of 153 Amrit Sarovars, the work on 42 is complete.
Similarly, the DDC also took stock of the physical and financial progress made under PMAY and Awas plus wherein he was informed that against the target of 30661 houses under PMAY-G, the work on as many as 16951 stands completed while against of target of 10864 houses under Awas plus, the work on 93 houses is complete. He also set Target for completion of 10000 PMAY houses in coming months.
Addressing the officers during the meeting, the DDC asked them to work with proper dedication and added zeal to meet the developmental expectations of the general public.
Asking the concerned officers to adhere to set timelines, he directed them to work meticulously utilising the working season besides, he also stressed on meeting quality parameters.
DDC also directed the concerned authorities to resolve the issues and remove bottlenecks, if any, on priority so that execution of works shall not be delayed.







Users Today : 61
Users Yesterday : 623
Users Last 7 days : 3664
Users Last 30 days : 8605
Users This Month : 5785
Users This Year : 9148
Total Users : 9149
Views Today : 64
Views Yesterday : 807
Views Last 7 days : 4957
Views Last 30 days : 13474
Views This Month : 8317
Views This Year : 14216
Total views : 14217
Who's Online : 7