Rajouri, May 09: In order to review the progress of construction of bunkers in the district being executed by Rural Development Department, the District Development Commissioner Mohammad Aijaz Asad today convened a meeting in his office chamber with the officers of REW ,RDD and revenue department.

The meeting was attended by Assistant Commissioner Revenue Mohd Ashraf, Executive Engineer REW Noor Ali Chowdary Rajouri, concernedTehsildars and concerned BDOs.

The Executive Engineer Assistant Commissioner Development,Rajouri Akhter Qazi informed the DDC that there are a total of 1892 bunkers which includes 1745 individual and 147 community bunkers are being executed by RDD out of which the work on 1068 bunkers have been started.

While taking stock of bunkers being executed by the PWD Rajouri and Nowshera division, it was informed that there are total 1249 bunkers both individual and community,out of which 1116 falls in Nowshera subdivision and 133 in Rajouri subdivision.It was informed that work on 312 bunkers in Nowshera and work on 72 bunkers in Rajouri have been started .

Meanwhile the DDC also took blockwise stock of distribution of material including steel and cement. He asked the nodal officer material and supplies of bunker construction Sh Puran Chand BDO Seri to ensure the proper distribution of material and take receipt of material supplied from every Block development officers.

Assistant Commissioner Development Rajouri breified DDC about the availability of material in the district exclusively for the construction of bunkers .He informed that 46775 bags of cement was received till date.

He directed the BDOs to prepare the list of sites identified for bunkers construction, appoint the GRS as incharges of bunker construction and deploy the men and machinery ,so that the progress can be achieved in prescribed time limits.

DDC made it clear that project has to be completed within the set timeline and no laxity will be tolerated in the case of spill over the deadline.

Leave a Reply

Your email address will not be published. Required fields are marked *

Poll

[democracy id="1"]

Share Market

Also Read This

Gold & Silver Price

today weather

Our Visitor

1 7 0 8 8 5
Users Today : 43
Users Yesterday : 155